Snow Clearing Updates – Mar 15 2017 – 8:00 am

Forecast as of 8:00am

90% POP of flurries until 8:00am, Icy road conditions until Noon today
High winds causing blowing and drifting snow throughout the day

Summary of winter maintenance activities
As of 8:00am Wednesday March 15, 2017
Arterial Road
Clean up operations, turn lanes and drifting locations to commence at 9:00am
AM clean up ongoing until 9:00am
5th round of salting completed 7:30am
Layby parking clean up completed 4:15 am

Collector Roads
5th round spot salting estimated completion 9:30 am

Local Roads
2nd round salting deployed 6:00pm March 14 completed 3:00am

Laneway Roads
Salters deployed 8:00am March 14 completed 6:30am
Humber Bay Waterfront Trail
5th round salting ( clearing drifting snow where required) estimated completion 11:30am

Sidewalks
Salting and Plowing deployed at 10:00am on High Pedestrian progressing to Low Pedestrian at 5:30 pm completed 8:30 pm
2nd round on High Pedestrian sidewalks commenced at 8:30pm completed 2:00am March 15
Manual clearing pinch points, steps and walkways until completed 2:00am March 15

Bus Stops and Crosswalks
Manual salting 10:00am March 15 completed 1:30am

Seniors Sidewalks
Senior program commenced 6:00am estimated completion 6:30pm

Download (PDF, Unknown)