Snow Clearing Updates – Feb 12 2017 – 6:30 pm

Forecast as of 6:30pm
Snow changing to rain at 6:00pm - 8:00pm
Icy roads until 1 am Monday Morning
Wind gusts up to 70kph at midnight

Summary of winter maintenance activities

As of 6:30pm on Sunday February 12, 2017
Arterial Road
AM clean up scheduled for 6:00am
Lay By Parking scheduled for 12:01 Feb 13
Clean up operations deployed 3:00pm
Windrow clearing deployed at 3:00pm
2 Rounds of Plowing completed 5:30pm

Collector Roads
3rd round Salting started at 6:25pm
Plowing deployed 12:01pm completed 5:30pm
2nd round salting completed

Local Roads
Clean up operations scheduled for 10:00am estimated completion 8:00pm Feb 13
2nd Round of Salting scheduled for 1:00am Feb 13
Plowing started by 5:30pm estimated completion 1:00am Feb 13
1st round salting commenced 7:30am estimated completion 7:30pm

Laneway Roads
Salting deployed 9:00am estimated completion 9:00am Feb 14

Humber Bay Waterfront Trail (Humber River to Mississauga Border)
3 rounds of salting and plowing completed by 4:30pm

Sidewalks
Sidewalk plowing and salting deployed at 5:00pm high then low pedestrian routes. estimated completion 7:00am Feb 13
Hand Crews deployed 5:00pm estimated completion 7:00am Feb 13

Bus Stops and Crosswalks
Bus Stop and crosswalks machines to be deployed at 8:00pm Feb 12
(48 hour operation)

Seniors Sidewalks
Senior program to Commence Feb 13, 6:00am

Snow Removal
No Activity