Snow Clearing Updates – Feb 25 2017 – 9:30 pm

Forecast as of 9:30pm
40% POP less than 1 cm of snow flurries through Sunday morning.
dry gusty conditions expected Sunday
.
Summary of winter maintenance activities
As of 9:30pm Saturday February 25, 2017

Arterial Road
Anti Icing Deployed 9:00pm estimated completion 1:00am Feb 26

Collector Roads
Anti Icing Deployed 9:00pm estimated completion 1:00am Feb 26

Local Roads
No Activity

Laneway Roads
No Activity

Humber Bay Waterfront Trail
No Activity

Sidewalks
No Activity

Bus Stops and Crosswalks
No Activity

Seniors Sidewalks
No Activity

Continue reading

Snow Clearing Updates – Feb 15 2017 – 10:00 pm

Forecast as of 10:00pm
Isolated flurries this evening, potential for icy conditions 9:00pm thru 5:00am Thursday
Gusty winds 45-55kph tonight

Summary of winter maintenance activities

As of 10:00pm on Wednesday February 15, 2017

Arterial Road
No Activity

Collector Roads
No Activity

Local Roads
No Activity

Laneway Roads
No Activity

Humber Bay Waterfront Trail (Humber River to Mississauga Border)
No Activity

Sidewalks
Spot Salting operation on High /low Pedestrian sidewalks 10:00am to 6:00pm
Hand crews spot salting walkways and steps from 10:00am to 6:00pm

Bus Stops and Crosswalks
Spot salting from 10:00am to 6:00pm

Seniors Sidewalks
Completed No Activity

Snow Removal
No Activity

Continue reading

Snow Clearing Updates – Feb 15 2017 – 3:00 pm

Forecast as of 3:00pm
60% POP rain/snow mix this evening, potential for icy conditions 9:00pm thru 5:00am Thursday
Gusty winds 45-55kph tonight
Summary of winter maintenance activities

As of 3:00pm on Wednesday February 15, 2017
Arterial Road
No Activity

Collector Roads
No Activity

Local Roads
No Activity

Laneway Roads
No Activity

Humber Bay Waterfront Trail (Humber River to Mississauga Border)
No Activity

Sidewalks
Spot Salting operation on High and Low Pedestrian sidewalks from 10:00am estimated completion 7:00pm
Hand crews spot salting walkways and stepts from 10:00am estimated completion 7:00pm

Bus Stops and Crosswalks
Spot salting from 10:00am estimated completion 7:00am

Seniors Sidewalks
Day3 program completed 11:00am

Snow Removal
No Activity

Continue reading

Snow Clearing Updates – Feb 15 2017 – 9:00 am

Forecast as of 9:00am
60% POP rain/snow mix overnight, potential for icy conditions at midnight
Summary of winter maintenance activities

As of 9:00am on Wednesday February 15, 2017
Arterial Road
No Activity

Collector Roads
No Activity

Local Roads
No Activity

Laneway Roads
No Activity

Humber Bay Waterfront Trail (Humber River to Mississauga Border)
No Activity

Sidewalks
Spot Salting operation on High Pedestrian sidewalks from 10:00am
Hand crews spot salting walkways and stepts from 10:00am

Bus Stops and Crosswalks
Spot salting from 10:00am

Seniors Sidewalks
Day3 6:00am until 12:00pm

Snow Removal
No Activity

Continue reading

Snow Clearing Updates – Feb 14 2017 – 3:00 pm

Forecast as of 3:00pm
60% POP rain/snow mix overnight, potential for icy conditions at midnight
Summary of winter maintenance activities

As of 3:00pm on Tuesday February 14, 2017
Arterial Road
No Activity

Collector Roads
No Activity

Steep Local Roads
Anti Icing 10:00 am completed 2:00pm

Local Roads
No Activity

Laneway Roads
No Activity

Humber Bay Waterfront Trail (Humber River to Mississauga Border)
No Activity

Sidewalks
No Activity

Bus Stops and Crosswalks
No Activity

Seniors Sidewalks
Day 2 6:00am until 2:00pm
Projected completion Feb 15 12:00noon

Snow Removal
Laneway frontage snow removal Feb 14 6:30am - 2:30 pm Completed

Continue reading

Snow Clearing Updates – Feb 14 2017 – 11:30 am

Forecast as of 11:30am
60% POP rain/snow mix overnight, potential for icy conditions at midnight
Summary of winter maintenance activities

As of 11:30am on Tuesday February 14, 2017
Arterial Road
No Activity

Collector Roads
No Activity

Steep Local Roads
Anti Icing 10:00 am estimated completion 3:00pm

Local Roads
No Activity

Laneway Roads
No Activity

Humber Bay Waterfront Trail (Humber River to Mississauga Border)
No Activity

Sidewalks
No Activity

Bus Stops and Crosswalks
No Activity

Seniors Sidewalks
Day 2 6:00am until 2:00pm
Projected completion Feb 15 12:00noon

Snow Removal
Laneway frontage snow removal Feb 14 6:30am - 2:30 pm

Continue reading

Snow Clearing Updates – Feb 14 2017 – 8:00 am

Forecast as of 8:00am
40% POP less than 1 cm snow flurries until noon
60% POP rain/snow mix overnight
Summary of winter maintenance activities

As of 8:00am on Tuesday February 14, 2017
Arterial Road
PM clean up 4:00pm completed 7:35pm

Collector Roads
No Activity

Local Roads
Clean up plow operations from 10:00am completed 6:00pm

Laneway Roads
No Activity

Humber Bay Waterfront Trail (Humber River to Mississauga Border)
No Activity

Sidewalks
No Activity

Bus Stops and Crosswalks
North of Eglinton only - Completed 8:00am Feb 14

Seniors Sidewalks
Day 1 6:00am until 5:30pm
Day 2 6:00am until 2:00pm
Projected completion Feb 15 12:00noon

Snow Removal
Laneway frontage snow removal Feb 14 6:30am - 2:30 pm

Continue reading

Snow Clearing Updates – Feb 13 2017 – 3:00 pm

Forecast as of 3:00pm
Icy conditions observed at RWIS stn until Noon and then wet only
Road temps above 0 to 5pm today, air temps above 0 after 9am Tuesday morning

Summary of winter maintenance activities

As of 3:00pm on Monday February 13, 2017
Arterial Road
AM clean up from 6:00am completed 9:35am
PM clean up scheduled to start at 4:00pm estimated completion 7:00pm

Collector Roads
4th round salting started 4:30am completed 9:35am

Local Roads
Clean up plow operations from 10:00am estimated completion 6:00pm
2nd round salting deployed 1:10am completed 11:30am

Laneway Roads
Salters deployed 9:00am Feb 12 completed 9:30am Feb 13

Humber Bay Waterfront Trail (Humber River to Mississauga Border)
Salt and plowing deployed 4:30am completed 10:45am

Sidewalks
No Activity

Bus Stops and Crosswalks
North of Eglinton only - Continuing 8:00pm this evening estimated completion 6:00am Feb 14

Seniors Sidewalks
Day 1 6:00am until 5:30pm
Day 2 6:00am until 2:30pm

Snow Removal
Laneway frontage snow removal scheduled for Feb 14 6:30am

Continue reading

Snow Clearing Updates – Feb 13 2017 – 8:00 am

Forecast as of 8:00am
Icy conditions observed at RWIS stn until 7am
Road temps above 0 from 10am to 5pm Monday
Chance of flurries through Monday morning
Wind gusts 50-70 km/h diminishing this morning
Summary of winter maintenance activities

As of 8:00am on Monday February 13, 2017
Arterial Road
AM clean up from 5:40am estimated completion 9:00am
Lay By Parking 12:01am completed 4:45am
3rd round salting deployed 8:35pm Feb 12 completed 11:50pm Feb 12
Clean up operations deployed 3:00pm Feb 12 completed 9:40pm Feb 12
Windrow clearing deployed at 3:00pm Feb 12 completed 1:00am

Collector Roads
4th round salting 4:30am estimated completion 9:30am
3rd round Salting 6:25pm Feb 12 completed 11:20pm Feb 12

Local Roads
Clean up plow operations scheduled for 10:00am estimated completion 6:00pm
2nd Round of Salting deployed 1:10am estimated completion 1:00pm
Plowing deployed 5:30pm Feb 12 completed 1:00am

Laneway Roads
Salting deployed 9:00am Feb 12 estimated completion 10:00am

Humber Bay Waterfront Trail (Humber River to Mississauga Border)
Salt and plowing deployed 4:30am estimated completion 11:00am

Sidewalks
Sidewalk plowing and salting deployed 5:00pm Feb 12 to plow and salt estimated completion 9:00am
Hand Crews deployed 5:00pm Feb 12 estimated completion 9:00am

Bus Stops and Crosswalks
Bus Stop and crosswalks machines deployed 8:00pm Feb 12 to 8:00am Feb 13 (south of Eglinton completed)
Continuing 7:00pm Feb 13 estimated completion 8:00am Feb 14 (north of Eglinton only)

Seniors Sidewalks
Day 1 6:00am until 5:30pm
3 day completion

Snow Removal
No Activity

Continue reading